SadCandidate6 t1_it88hhb wrote

12A is 28A and 12B is 28B...

There is no C

1

monkysandtools t1_it8htuz wrote

What ended up happening;
12B (113 West and I-295 North) turned into 28 A and C
12A (113 East) turned into 28 B

What should have happened
12B turns into 28 C and B (I-295 N and 113 West)
12A turns into 28 A (113 East)

Even Google Maps got it messed up right now (Claiming both exits as 28B)

2

WhyPartyPizza OP t1_it9o3gg wrote

UPDATE: Contacted RIDOT.

Their response:

Good morning,

Thank you for reaching out. I will forward the below issue to the project manager. Once I have received a response, I will follow up with you.

2

SadCandidate6 t1_it894v3 wrote

If there's a sign that shows C, then it must be a mistake unless they are adding a ramp or something

But I totally get what you mean. I want to go drive down by it so I can check it out haha. Theres all kinds of discrepancies throughout this new mile market exit numbers crap.