Aroon164 t1_je6r3ok wrote

The board was Baker appointed from the beginning. GLX has never been on track over budget and behind schedule from the beginning. AFC 2.0 is the same. Green line train protection is even worse. The orange and red line trains speak for themselves. What did they get correct? They had a 3 year moratorium on the tax payer protection act and all they did was give private contractors capital projects that went over budget and behind schedule.